We are constructing our site plans using Civil 3D. Figure 1 exemplifies the site plan. We are currently coming up with different alternative projects using different locations and types of projects. We started calculating how many new students TCNJ will be adding to the school. After our calculations and researching important documents ,such as TCNJ Transformation 2.0, we were able to come up with the idea that there will be about 600 students being added. Therefore, we will be constructing a dormitory that will account for about 650 or more students. We are starting to compare the hydraulic analysis of Green Field to see where the best locations of our building would be. For the structural component we are deciding the dimensions of the dormitory and discussing if we want to construct the building with steel or concrete. A goal for the upcoming month is to finalize the alternative designs and pick a specific location on Green Field for our building! Figure 1: Site Plan made in Civil 3D